Stites Hill Road & Rydons Lane

Stites Hill Road & Rydons Lane

We are investing over £150,000 in an important water mains renewal in Stites Hill Road and Rydons Lane to secure safe and reliable drinking water supplies for homes and businesses in the area. 

Project updates

Why is this work necessary?

What does it involve?

Traffic management

Timetable of work

Will water supplies be cut off?

Keeping you informed


Project updates

14 February 2018

All works are now complete on Sites Hill Road, and the road is fully open. This has been a challenging project which has involved laying approximately 544 meters of new high performance polyethylene pipe, and renewing the service connections to all properties. Part of this project also involved negotiating around two high pressure gas mains - a very tricky task to complete.

We plan to the start mains replacement in Rydons Lane at the end of February 2018. We are currently in discussions with Croydon Council to confirm an exact start date.    

We would like to thank you for your co-operation and patience during these essential works.

---

2 February 2018

Works are progressing well on Stites Hill Road with approximately 564m of main laid to date. As part of this project we have had to lay the new water main over two high pressure gas mains. This has proven a complex operation but with the aid of Southern Gas Networks and our own specialist contractor Clancy Docrwa we are confident the project will still be delivered time.

We are still working under a full road closure and we kindly ask that all road users follow the signed diversion route. Access is being maintained for residents and emergency services. We estimate all works and the closure to be removed from Stites Hill Road week commencing 12 February 2018.

We hope to start works in Rydons Lane at the end of February 2018, we are currently in discussions with Croydon Council to confirm the start date.    


19 January 2018

Stites Hill Road
Works are continuing to progress well on Stites Hill Road with approximately 400m of main laid to date. We are still working under a full road closure and we kindly ask that all road users follow the signed diversion route. Access is being maintained for residents and emergency services. We ask that all other road users follow the signed diversion route.

Rydons Lane 
We have decided to postpone the Rydons Lane phase of this project. Our current programme indicates that we will be commencing work on this phase of the project in April, however we will post more information on this page as soon as dates are confirmed.

For further information or to discuss your individual needs, please contact our Customer Services Operations team on 01737 772000, option 1

We sincerely apologise for any inconvenience these essential works may cause and thank you for your co-operation and patience.

---

12 January 2018

Stites Hill Road
Following the Christmas break works have now recommenced with a road closure on Stites Hill Road. Access is being maintained for residents and emergency services. We ask that all other road users follow the signed diversion route.

Rydons Lane
We have decided to postpone the Rydons Lane phase of this project. Details of the revised start date will be posted on this page in due course.

For further information or to discuss your individual needs, please contact our Customer Services Operations team on 01737 772000, option 1

We sincerely apologise for any inconvenience these essential works may cause and thank you for your co-operation and patience.

---

22 December 2017

Stites Hill Road
Works will cease today and all traffic management will be removed for the Christmas period.

We will be returning to site on 2 January to continue with mainlaying phase on Stites Hill Road.

We would like to wish you all a very merry Christmas and a happy new year.

---

15 December 2017

Stites Hill Road
Works commenced on 11 December and we are pleased to say that we are already ahead of programme. We will be continuing to work seven days a week until the Christmas period.

In order to carry out these works safely we have had to close Stites Hill Road to all traffic, however access will be maintained for residents and emergency services. We ask that all other road users follow the signed diversion route.

We will be ceasing work and lifting the road closure for the Christmas Period. All traffic management will be removed on Friday 22 December and will be reinstalled on Tuesday 2 January.

We sincerely apologise for any inconvenience these essential works may cause and thank you for your co-operation and patience


Why is this work necessary?
The existing water main cannot cope with the demand of an increasing local population which is heightened by new property developments in the area. Installing a new, wider main will increase the current capacity.

Also, many mains in this area were laid in the Victorian era and the pipes are now reaching the end of their operational life so need replacing. 

What does it involve?
The project will involve laying approximately one kilometre of new main along Stites Hill Road and Rydons Lane and new pipe connections will be made to properties. The existing main will be decommissioned.

Traffic management
Due to the location of the existing water main and a number of other utilities already in the ground, we will be required to work in the public highway. Therefore, traffic management, including road and junction closures, will be required to keep pedestrians, motorists and our workforce safe. 

Closures are used when we are unable to provide the required legal distances around our works but all customers will still be able to access their properties. 

All roadworks and necessary diversions will be advertised on our website at seswater.co.uk/StitesHillAndRydons and information boards will be visible in the affected areas prior to any closure being implemented.

Our delivery partner Clancy Docwra will be working 7:30am to 5pm Monday to Friday (and weekends where required).

Timetable of works

The project will be split into two phases:

Phase 1: Stites Hill Road (click on map to enlarge)
We will start the site set-up week commencing 11 December and aim to complete this phase by spring 2018. A road closure will be in place until February 2018 but will re-open for two weeks from 22 December for some respite over the Christmas break.

Once the new main has been laid and tested, we will need to return to connect three properties which may require a short-term road closure (two days). This work may be carried out over a weekend if requested.  

 

 

 

 

 

 

 

 

 

 

 

 


 

Phase 2: Rydons Lane(click on map to enlarge)
We have decided to postpone the Rydons Lane phase of this project. Details of the revised start date will be posted on this page in due course.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Will water supplies be cut off?

Water supplies will continue as normal while the old water main is being replaced but there will be a temporary interruption of between 30 and 60 minutes as your property is connected to the new main. Customers will be notified in advance of this happening.

Keeping you informed

We have contacted all customers within the catchment area of the two phases to give residents and business some more detailed information.

This page will be updated regularly to provide information on our progress.

Customer can also keep up to date on twitter @SESWater or Facebook @SESWaterOfficial.

For further information or to discuss your individual needs, please contact our Customer Services team on 01737 772000, option 1 or you can email the team CustomerServicesOPS@seswater.co.uk referencing M0006827

 


"